FISCAL YEAR 2024 PUBLIC NOTICE FOR AIRPORT PROJECTS

The Town of Vivian, LA as sponsor for the Vivian Airport hereby announces its proposed Fiscal Year 2022-2024 Triennial DBE Goal for Disadvantaged Business Enterprise (DBE) airport construction projects as indicated below. Please note the airport is amending its existing fiscal year 2022-24 DBE goal to add a fiscal year 2024 project. Prior year projects are complete or in progress and are only included for informational purposes.

Fiscal Year 2022: 7.66%
Runway/Taxiway Improvements (Taxiway Turnarounds)

Fiscal Year 2023:
No Federally Funded Project

Fiscal Year 2024: 6.76%
Base Bid: Runway 9-27 Rehabilitation: 6.58%
Alternate No. 1: Taxiway Turnaround Rehabilitation: 7.32%
Alternate No. 2: Apron Rehabilitation: 7.41%

Overall Three-Year DBE Goal FY22-FY24: 7.46%
A teleconference will be held on April 5th, 2024 from 9:00 AM to 9:30 AM Central Standard Time for the purpose of consulting with stakeholders to obtain information relevant to the goal setting process. If you would like to comment on the proposed DBE goal, please dial into the teleconference at (415) 464-6800 with conference code 2180581# or email lspillers@dbeplans.com.

The airport’s DBE goal methodology is based on what the airport anticipates receiving for FY 2022-2024. Significant changes to the projects as stated will require an amendment to the DBE goal.